HD1 South Transfer Pump Station

Project Scope

Design, supply and commission pump station for 3 x 300kW drives and associated infrastructure

Location

Iron Ore Mine Site, Pilbara WA

Project Overview

Design and construction of:

  • 33kV power pole modifications.
  • 33kV underground cable and pit installations.
  • 33kV to 415V 1MVA transformer kiosk.
  • MCC with 300kW VSDs, L&SP, Control PLC, Internal aircon.
  • 3 x 300kW motors and pumps feeding main pipeline.
  • 1 x 18.5kW motors and pump feeding stand-pipe.
  • Cable ladder installations above head height with waterfalls.

Project Instrumentation included flow meters, level sensors, pressure sensors and flow switches

Scope included full commissioning of instrumentation  and control system and handover to client