The Design and Construct Project included modification to 33 bores across both sites, transfer piping upgrades to saline dam pump stations and booster stations, new flow monitoring stations and partial demolition of existing infrastructure.
All the Civil, Mechanical and Electrical works were self-performed by ADENCO with bores installed using its custom designed and manufactured Bore Installation rig, which enables safe installation and retrieval of the downhole pump with the operation via a wireless handheld control unit.
Kaltails Borefield
- Installation and modification to the Kaltails Bore Field composed of 18 bores in total
- Construction of transfer and branch piping, ranging in size from D160 to DN560 with a total length of 33km of pipe installed
- Partial demolition and upgrade of the Kaltails Transfer Station
- Upgrade of the Kaltails Saline Dam pump station
Gidji Borefield
- Installation and modification to the GidjiBore Field composed of 15 bores in total
- Construction of transfer and branch piping, ranging in size from DN110 to DN500 with a total length of 40km of pipe installed
- Upgrade of three Gidji Booster Pumping Stations
- Supply and installation of three flow monitoring stations