Design and construction of:
- fire water system including containerised pumps and two storage tanks
- potable water system, including a treatment unit and two storage tanks
Construction of:
- new pit surface dewatering system including two new skid mounted pumps
- new pit bore dewatering system including eight new bore pump assemblies
- process water system including a transfer pipe main and five water pumps
- surplus water system including an 8km transfer pipe main
- water supply tie-in pipeline, including tie-ins to the existing pipe network
- new heavy vehicle water cart fill station
- new light vehicle water cart fill station
- All testing and commissioning works to verify the system
Total of 59km of HDPE piping and 23km of power, control and instrumentation cable installed